Post by isavelar » Mon Feb 21, 2011 6:27 am

Good Morning!!!

I have a system of cameras of your company and I also have two AMTI force platforms and would like the ability to synchronize the two systems, the possibility?
I hope the return

NaturalPoint - Mike
Posts: 1896
Joined: Tue Feb 01, 2011 8:41 am
Location: Corvallis, OR

Re: Syinc with force plate AMTI and Optitrack

Post by NaturalPoint - Mike » Tue Feb 22, 2011 4:16 pm

Possible, yes. However you will be in for some development work. V100R2 cameras can sync via a device we make called the OptiHub. The OptiHub features a sync in and sync out port that allows hardware synchronization to third party devices. Software will be a bit more involved, as we do have an API and several SDKs available, however significant development would be required on your part to integrate properly. We are, however, more than willing to answer questions and help where we can if you decide to do this.

Thanks!

urbanolu
Posts: 3
Joined: Thu Jan 05, 2012 4:12 am

Re: Syinc with force plate AMTI and Optitrack

Post by urbanolu » Thu Jan 05, 2012 5:09 am

Hi everyone,

We have two AMTI AccuGait force plates at our gait lab, along with 12 V100R1 cameras and one OptiHub. We have managed to synchronize both systems by using the following procedure:

1. Set both systems (cameras and force plates) to use a 100 Hz sampling frequency.
2. Connect the sync out port of the OptiHub (BNC) to the trigger in port of the AMTI PJB-101 box (RCA).
3. In the AMTI NetForce software, set external source (rising edge) as trigger method.
4. In the Arena software, adjust the camera synchronization settings as follows:
-OptiHub Sync Control: Custom Synchronization.
-Sync Mode: Wired-Sync (R1 cameras lack the OptiSync feature).
-Pulse Type: Recording Level.
-Polarity: Active Low.

As soon as Arena starts recording, the OptiHub will output a constant voltage through the sync out port, which triggers the force capture if the NetForce trigger is armed. Obviously, this does not synchronize every frame, just the capture startup. We have checked the synchronization by attaching a marker to a soft hammer and hitting the plates, then verifying that the force and trajectory peaks coincide in time.

I hope this helps...

fequalsma21
Posts: 3
Joined: Wed Feb 12, 2014 12:37 pm

Re: Syinc with force plate AMTI and Optitrack

Post by fequalsma21 » Sat Apr 12, 2014 7:08 am

Thanks @Urbanolu for those settings. I'm using an AMTI OR6-7 series force plate and have purchased an esync to be used with a bank of s250e cameras. In Arena (v.1.800) I seem to keep getting an error message (see attached picture). Any chance you have seen that before?

Thanks,
Jeev
Attachments
Capture.PNG
Capture.PNG (252.6 KiB) Viewed 4086 times

Luisa
Posts: 1
Joined: Fri Sep 18, 2020 1:00 pm

Re: Syinc with force plate AMTI and Optitrack

Post by Luisa » Fri Sep 18, 2020 1:08 pm

Hi everyone,
do you know if this is possible with Motive (Flex3 cameras)?

Thanks,
Luisa

urbanolu wrote:
Thu Jan 05, 2012 5:09 am
Hi everyone,

We have two AMTI AccuGait force plates at our gait lab, along with 12 V100R1 cameras and one OptiHub. We have managed to synchronize both systems by using the following procedure:

1. Set both systems (cameras and force plates) to use a 100 Hz sampling frequency.
2. Connect the sync out port of the OptiHub (BNC) to the trigger in port of the AMTI PJB-101 box (RCA).
3. In the AMTI NetForce software, set external source (rising edge) as trigger method.
4. In the Arena software, adjust the camera synchronization settings as follows:
-OptiHub Sync Control: Custom Synchronization.
-Sync Mode: Wired-Sync (R1 cameras lack the OptiSync feature).
-Pulse Type: Recording Level.
-Polarity: Active Low.

As soon as Arena starts recording, the OptiHub will output a constant voltage through the sync out port, which triggers the force capture if the NetForce trigger is armed. Obviously, this does not synchronize every frame, just the capture startup. We have checked the synchronization by attaching a marker to a soft hammer and hitting the plates, then verifying that the force and trajectory peaks coincide in time.

I hope this helps...

steven.andrews
NaturalPoint Employee
NaturalPoint Employee
Posts: 579
Joined: Mon Jan 19, 2015 11:52 am

Re: Syinc with force plate AMTI and Optitrack

Post by steven.andrews » Tue Sep 22, 2020 10:24 am

Hello Luisa,

Force plate integration is not supported for the Flex cameras and the OptiHub.

With Motive and your Flex system, you can try to configure a setup similar to what is described in the message you shared. That may work, but it is possible there will be some drift between the motion capture and the force plates during recording. True synchronization between the systems would require the use of our Ethernet cameras with an eSync.